OUR RESULTS

Maximizing operational output. Under budget and Ahead of Schedule.

SDS successfully drilled, cased and suspended its first cotton valley well in Harrison Co., TX. The 15,800’ well was completed in 8-3/4” hole with 5-1/2” casing.

SDS successfully drilled, cased and suspended a 4 well pad in Martin Co. 2 HZ wells will be completed in the Wolfcamp and 2 in the Sprayberry. All 4 wells were 2 mile laterals.

SDS successfully drilled, cased, and suspended another Strawn sand well in Scurry Co., TX.  The 12581’ well was SDS’s 8th strawn sand well to drill.

SDS successfully drilled, cased, and suspended another Strawn sand well in Scurry Co., TX.  The 14447’ well was SDS’s 7th strawn sand well to drill.

SDS successfully drilled, cased, and suspended another Strawn sand well in Scurry Co., TX.  The 14035’ well was SDS’s 6th strawn sand well to drill.

Oil & Gas Project Management
Oil & Gas Project Management

SDS successfully drilled, cased, and suspended it’s 5th Strawn sand well in Scurry Co., TX.  The 14180’ well was SDS’s 5th strawn sand well drilled.

SDS successfully drilled and completed a 13,000’ Ellenburger disposal well in Martin Co., TX.  The 3 string design with an open hole Ellenburger completion was a success.  The completion included a 5-1/2” injection string.  This is SDS’s 4th Martin Co Ellenburger well to complete on full project management.

SDS successfully drilled and completed a 13,700’ Ellenburger disposal well in Midland Co., TX. The 3 string design with an open hole Ellenburger completion was a success. The completion included a 5-1/2” injection string.

SDS successfully drilled, cased, and suspended it’s 3rd Smackover brine supply well in Columbia Co., AK. The well was an extended reach well at with a 65° tangent through the under-pressured Smackover. The 12,700’ MD well was completed in 22 days.

The well design included a 70-degree tangent through the Smackover formation, and the well was drilled to a total depth of 11,598’ with a Patterson 591.

26 days from spud to rig release, shattering the previous in-field record of 33 days.

SDS Project Management Team drills and completes San Andres SWD in Dawson Co., TX. SDS successfully drilled and completed a 5800’ San Andres disposal well in Dawson Co., Tx.

  • The well took 12 days to drill, case and complete.
  • Operations were completed ahead of the plan and under budget.

SDS successfully drilled, cased and completed its second of three Ellenburger SWD wells in Martin Co., TX.

The well design included:

Intermediate casing set through San Andres and encountered H2S while drilling into injection zone. Drilling liner set into top of Ellenburger while experiencing multiple lost circulation zones throughout the interval. Ellenburger was successfully drilled and logged without incident.

The depth the well was drilled with the Scan Pride: 14,000’

SDS Project Management Team successfully drills Strawn well in Scurry Co. TX.

  • The 14,580’ well was drilled in 24 days.
  • Operations were completed 6 days ahead of the plan and under budget.

SDS Project Management Team successfully drills Strawn well in Scurry Co., TX.

  • The 15,020’ well was drilled in 21 days
  • Operations were completed 8 days ahead of the plan and under budget

SDS has 3 operators committed to drilling 13 wells between Scurry and Martin Counties. Also on the books is a potential second rig line in Martin Co. with 4 to 8 wells to drill.

SDS successfully drilled, cased and suspended its 4th Strawn horizontal well in Scurry Co., TX in 2021.

  • The 15,086’ well was drilled in 22 days.
  • Operations were completed ahead of the plan and under budget.

SDS successfully drilled, cased and suspended a 5905’ Viola horizontal well in Stafford Co., KS.

  • The well took 8 days to drill, case and suspend.
  • It’s one of the first successful horizontal wells drilled in the Viola.
  • Operations were completed ahead of the plan and under budget.
Oil and Gas Engineering
Drilling Engineering

Ready for Extraordinary Results?

Partner with SDS Project Management to help you maximize your operational performance, reduce expenditures and reach optimal potential. If you’re ready to work with the best, contact us today to begin your consultation.

Scroll to Top